National Grid Transco (NNGD) Q2 2027 Earnings Report

0 Followers

DE:NNGD Q2 2027 EPS Results

Actual EPS
EUR 2.20
Consensus EPS
EUR 2.05
Beat/Miss
Beat by +EUR 0.15
One Year Ago EPS
EUR 1.75

DE:NNGD Q2 2027 Revenue Results

Actual Revenue
EUR 9.62B
Expected Revenue
EUR 9.09B
Beat/Miss
Beat by +EUR 525.47M
YoY Revenue Growth
+13.31%

Earnings Announcement Details

Quarter
Q2 2027
Date
11/05/2026
Time
Before Open
Conference Call
Thursday, November 5, 2026
DE:NNGD Upcoming Earnings

National Grid Transco's next earnings date is estimated for May 20, 2027, based on past reporting schedules.

Q2 2027 Earnings Call Audio

DE:NNGD Q2 2027 Earnings Call
0:00 / 0:00

Q2 2027 Earnings Slide Deck

Q2 2027 Earnings Call Summary

Q2 2027
Earnings Call Date:Nov 05, 2026|% Change Since:0.00%|
Earnings Call Sentiment|Positive

The call was predominantly positive. National Grid reported strong earnings growth, record capital investment, upgraded FY '27 guidance, substantial project and supply-chain progress, improved operational productivity and confidence in its FY '31 framework. The principal challenges were higher debt and finance costs, lower operating cash-flow growth guidance, cost pressures, a New England profit decline, the EGL 1 delay and uncertainty around selected non-regulated projects.

Company Guidance

National Grid now expects full year investment of GBP 13.5 billion, putting it on the run rate required to deliver at least GBP 70 billion by the end of FY '31, with full year EPS growth guidance upgraded to 15% to 16%; its 5-year framework remains at least GBP 70 billion of capital investment, underpinning around 10% annual asset growth and underlying EPS growth of 8% to 10% per annum from the FY '26 baseline. The company expects net debt to increase by a further GBP 4 billion, including the remaining Joulent funding, expects to maintain credit metrics above its current thresholds to at least FY '31, and continues to offer a progressive inflation-protected dividend policy. It is reaffirming planned ED3 investment of GBP 9 billion over the coming 5 years, has not changed its view on the GBP 40 billion U.K. investment outlook over the next 5-year period, and expects regulated controllable cost growth CAGR to be below U.K. CPIH over the 5-year period to FY '31.

  • Record Capital Investment and Upgraded GuidanceFirst-half capital investment increased 32% to GBP 6.7 billion, a record first-half level. Full-year investment guidance was upgraded to GBP 13.5 billion, supporting the run rate required to deliver at least GBP 70 billion by the end of FY '31.
  • Strong Earnings Growth and Higher EPS GuidanceUnderlying operating profit increased 13% to GBP 2.6 billion, while underlying EPS increased 22% to 36.5p. The company slightly upgraded full-year EPS growth guidance to 15% to 16%, supported by stronger business performance and two one-off fair value gains within National Grid Partners.
  • Progressive Dividend IncreaseThe Board declared an interim dividend of 16.97p per share, representing a 3.8% year-on-year increase and 35% of last year's full-year dividend, consistent with the policy of delivering an inflation-protected progressive dividend.
  • Supply Chain De-RiskingNational Grid secured over GBP 3 billion of additional delivery mechanisms during the first half, taking the total supply chain coverage for the broader program to over 80%. The company also has 100% of the critical primary supply chain for ASTI projects secured.
  • Organizational Simplification and AccountabilityThe company simplified its operating model, reduced the group executive committee from 13 members to 8, and aligned the organization behind newly formed U.K. and U.S. businesses supported by enterprise-wide capital, technology and innovation capabilities.
  • U.K. Transmission Investment SurgeU.K. electricity transmission investment increased 71% to GBP 2.9 billion in the first half, primarily reflecting ASTI investment of GBP 1.5 billion and other projects to reinforce the network and connect new generation.
  • Strong ASTI Execution and Project MilestonesAll six Wave 1 ASTI projects are in construction, with 100% of the critical primary supply chain secured. The company identified a 100-day schedule improvement on EGL 1 through generative scheduling, while Yorkshire Green and EGL 2 are tracking ahead of schedule. The 2.2-kilometer Thames Crossing for Grain to Tilbury was completed 49 days ahead of schedule.
  • ASTI Expansion and Planning ProgressASTI represents around GBP 17 billion of investment over the next five years. The first two Wave 2 projects at Pentir to Trawsfynydd are in construction, development consent was secured for Sea Link, DCO submissions were made for EGL 3 and EGL 4, and all remaining ASTI project planning submissions are expected by the end of March 2027.
  • Increased Generation ConnectionsNational Grid connected 2.5 gigawatts of generation in the first half, including the Sofia Wind Farm and the U.K.'s fourth-largest battery project in Newport. This was more than double the generation connected during the whole of FY '26.
  • U.K. Distribution Investment and ED3 PlanElectricity distribution investment increased 10% to GBP 834 million, driven by asset health, connections and load-related network reinforcement. The ED3 business plan is reaffirming planned investment of GBP 9 billion over the next five years, 40% higher than the previous period.
  • U.S. Rate Base and Investment GrowthThe U.S. rate base has grown by over 70% since 2020. New York investment increased 11% to GBP 1.8 billion, while New England investment increased 14% to GBP 1.1 billion, supported by network resilience, industrial and consumer demand, system capacity and modernization.
  • Micron Semiconductor Connection and Regional Economic ImpactWork commenced on the first phase of the electricity connection for Micron's semiconductor manufacturing site in Upstate New York, supporting an initial 480 megawatts of demand. At full build, demand is expected to reach around 2 gigawatts. The project is expected to support more than $100 billion of investment in Central New York, approximately 9,000 direct jobs and almost 50,000 broader regional economy and supply-chain jobs.
  • Operational Productivity ImprovementsThe Lighthouse productivity pilot helped crews reach first jobs 15% faster, reduced travel time between jobs by 25%, enabled up to one-third more valve inspections each day, and cut unplanned overtime on Long Island by 75%. The program is being rolled out across Upstate New York Gas.
  • Improved Customer Service MetricsNew England first-time billing accuracy improved to over 96%, up 2 percentage points from the prior year. AMI meter deployment increased tenfold over the same period, alongside improved customer satisfaction scores across the U.K. and U.S.
  • Affordability and Customer Support InitiativesNational Grid enrolled over 65,000 additional U.S. customers in low-income discount rates over the past year. U.K. interconnectors have generated GBP 400 million in payments to consumers over the past 3.5 years, with a further GBP 300 million forecast over the next 2.5 years, subject to Ofgem approval.
  • Technology and AI DeploymentThe company is scaling technology and AI tools to improve capital delivery, productivity, network capacity, asset reliability, cyber defenses and customer experience. Examples include Sensat infrastructure mapping, Exodigo underground mapping, Envelio capacity analytics, the Kraken platform for 6.5 million U.S. customers and Amazon Connect for 8 million U.K. distribution customers.
  • Workforce Expansion and Skills InvestmentNational Grid hired more than 3,600 people in the first half, with 90% recruited into operational businesses, including over 400 graduates and apprentices. It also committed GBP 5 million to practical training and qualifications for 5,000 young people in the U.K.
  • Joulent and Project Kilby Growth OpportunityNational Grid invested GBP 941 million in the Joulent joint venture during the first half and expects the remainder of the full GBP 1.3 billion to be deployed in the coming months. Project Kilby is a 2.7-gigawatt co-located data-center power facility in West Texas with a 50-50 Chevron joint venture, secured turbines and critical equipment, and a signed 20-year power purchase agreement with Microsoft. First power is targeted for 2028.
  • Resilient Long-Term Financial FrameworkThe company remains on track for at least GBP 70 billion of capital investment, around 10% annual asset growth and underlying EPS growth of 8% to 10% per annum from the FY '26 baseline through FY '31. Management expects to maintain credit metrics above current thresholds through at least FY '31.
  • Strong Operating Cash GenerationCash generated from operations increased 14% to GBP 4.1 billion compared with the prior year.
  • Regulatory and Policy ProgressNational Grid submitted a one-year rate stabilization proposal for KEDNY and KEDLI that would keep customer bills flat for one year in the current affordability environment. It also supported a Senate bill intended to speed permitting and reduce the cost of energy infrastructure, and set a long-term ambition for 70% of future U.K. supply-chain spend to be delivered in the U.K.

DE:NNGD Earnings History

DE:NNGD earnings history
Report DateFiscal QuarterForecast / EPSLast Year's EPSEPS YoY ChangePress Release
May 20, 20272027 (Q4)3.43-2.91――
Nov 05, 20262027 (Q2)2.052.201.7525.97% (+0.45)
May 14, 20262026 (Q4)2.902.912.746.44% (+0.18)
Nov 06, 20252026 (Q2)1.651.751.636.90% (+0.11)
May 15, 20252025 (Q4)2.522.742.4213.22% (+0.32)
Nov 07, 20242025 (Q2)1.591.631.235.86% (+0.43)
May 23, 20242024 (Q4)2.362.421.9424.64% (+0.48)
Nov 09, 20232024 (Q2)1.181.201.42-15.10% (-0.21)
May 18, 20232023 (Q4)1.931.943.09-37.19% (-1.15)
Nov 10, 20222023 (Q2)1.411.420.58143.54% (+0.84)

The table shows recent earnings report dates and whether the forecast was beat or missed. See the change in forecast and EPS from the previous year.

Beat Missed