DE:NE0 Q3 2026 EPS Results

Actual EPS
-EUR 0.43
Consensus EPS
EUR 0.56
Beat/Miss
Missed by -EUR 0.98
One Year Ago EPS
EUR 0.33

DE:NE0 Q3 2026 Revenue Results

Actual Revenue
EUR 841.13M
Expected Revenue
EUR 867.93M
Beat/Miss
Missed by -EUR 26.80M
YoY Revenue Growth
+22.77%

Earnings Announcement Details

Quarter
Q3 2026
Date
10/29/2026
Time
After Close
Conference Call
Thursday, October 29, 2026
DE:NE0 Upcoming Earnings

Nexa Resources SA's next earnings date is estimated for February 17, 2027, based on past reporting schedules.

Q3 2026 Earnings Call Audio

DE:NE0 Q3 2026 Earnings Call
0:00 / 0:00

Q3 2026 Earnings Slide Deck

Q3 2026 Earnings Call Summary

Q3 2026
Earnings Call Date:Oct 29, 2026|% Change Since:-17.76%|
Earnings Call Sentiment|Positive

The call was broadly positive. Nexa reported substantially higher Adjusted EBITDA, stronger revenue, positive free cash flow, lower leverage, improved Aripuanã utilization, recovering smelting operations, supportive zinc and copper markets, and continued progress at Cerro Pasco. These positives were partly offset by the $47 million net loss from a non-cash impairment, lower copper grades and development constraints in Peru, higher smelting and Aripuanã-related costs, pressure on treatment charges, credit-rating actions, and ongoing safety, permitting, and market uncertainties.

Company Guidance

Nexa raised 2026 CapEx guidance by 10% to $420 million, including a $41 million 2026 budget for Cerro Pasco, while production and sales guidance for the year remains unchanged; the fourth quarter is expected to be our stronger quarter of the year, copper is expected to finish at the lower end of the range, cash cost guidance was lowered, year-to-date cash cost is negative at $0.45 per pound towards the lower end of the new range, and cost per ton of run-of-mine is $55.07 near the top of the range with an expected improvement in the fourth quarter. At Aripuanã, plant utilization reached 90% in September, is expected to continue to improve in the next quarter, and the company expects to deliver 100% of capacity in the coming months, with first quarter full capacity; zinc production should remain stable in the fourth quarter. Cerro Pasco is expected to reach mechanical completion in December, with commissioning activities in the first quarter of 2027, operating authorization in the second quarter, and pumping starting in the early third quarter of 2027; approvals are now expected in March and April 2027. Smelting cash cost guidance was raised, with nine-month cash cost at $1.50 per pound within the new range, while higher fourth-quarter volumes should dilute fixed costs and keep conversion cost within the new range; silver production is expected to be 10 million to 11 million ounces this year.

  • Adjusted EBITDA Reached the Highest Level of 2026Third-quarter Adjusted EBITDA reached $301 million, the highest of the year, up 62% from a year ago and 5% from the second quarter, with a 32% margin. Higher zinc prices, stronger byproduct contributions, the recovery in smelting sales, and higher realized treatment charges more than offset higher operating and raw material costs.
  • Revenue and Adjusted Earnings ImprovedNet revenues totaled $937 million, up 3% from the second quarter and 23% from the same period last year. Excluding the impairment and other items, adjusted net income was $144 million and adjusted earnings per share were $0.87.
  • Free Cash Flow and Leverage ImprovedThe company generated $73 million in free cash flow. Net leverage decreased to 1.24 times from 1.4 times in June and 2.21 times a year ago, driven by last-12-month Adjusted EBITDA of almost $1.2 billion. Cash and cash equivalents increased by $25 million to $405 million.
  • Mining Segment Delivered Stronger ResultsMining net revenues were $454 million and Adjusted EBITDA was $236 million, up 7% from the second quarter and 44% year-over-year. The segment's EBITDA margin reached 52%, up 10 percentage points from the second quarter.
  • Zinc Production IncreasedZinc production reached 85,000 tons, up 7% from the second quarter and 1% from last year, driven mainly by Aripuanã, Vazante, and El Porvenir. The company said fourth quarter production is expected to be the stronger quarter of the year, while full-year production guidance remains unchanged.
  • Aripuanã Achieved Record Throughput and Higher UtilizationAripuanã treated a record 471,000 tons of ore, up 18% from the second quarter, while zinc production rose 48% to 13,000 tons, matching its best quarter. Plant utilization averaged 84%, up from 71% in the second quarter, and reached 90% in September. The fourth filter handled 61% of all tailings filter volume in the quarter and was performing well.
  • Aripuanã Expansion and Ramp-Up Remain on TrackThe company is accelerating mine development at Aripuanã to open more mining fronts and support higher throughput in 2027. Management expects utilization to reach 100% capacity in the coming months and said the operation is expected to begin reducing costs in the third quarter and in the next year, with the operation potentially becoming similar to other Brazilian operations toward the end of next year.
  • Smelting Production RecoveredSmelting production reached 159,000 tons, up 28% from the second quarter and 8% from last year, driven by the recovery at Cajamarquilla and processing of cathode inventory built up after the fire. Smelting Adjusted EBITDA was $65 million, broadly stable sequentially and nearly three times higher than a year ago, with a 9% margin.
  • Cajamarquilla Inventory Supports Fourth-Quarter SalesCajamarquilla operated normally throughout the quarter after the May fire, and sales volumes recovered. The inventory buildup positions the company to meet seasonally stronger fourth-quarter demand, supporting unchanged full-year sales guidance.
  • Byproduct Sales and Contributions StrengthenedThe year-over-year revenue improvement included a $65 million higher byproduct contribution. Sulfuric acid sales increased 18% from the second quarter to 178,000 tons, while silver and copper cement sales each increased 14%. Management highlighted sulfuric acid and silver recovery capabilities as support for smelter margins.
  • Mining Cash Costs ImprovedMining cash cost net of byproducts was negative $0.64 per pound, better than both the second quarter and the prior year, mainly due to stronger byproduct contributions, lower costs, and higher zinc sales at Aripuanã. The company lowered its 2026 cash cost guidance, reflecting much higher byproduct prices, and year-to-date cash cost was negative $0.45 per pound toward the lower end of the new range.
  • Cerro Pasco Construction Progressed as PlannedAt Cerro Pasco, the company completed all civil works, major equipment assembly, the access road, and the raise of the Atacocha Dam. Pre-commissioning and commissioning are underway, with mechanical completion expected in December, commissioning activities in the first quarter of 2027, operating authorization for the pumping system expected in the second quarter, and pumping expected to start in the early third quarter of 2027.
  • Cerro Pasco Investment Was AcceleratedThe company invested $15 million in Cerro Pasco during the quarter and $31 million year-to-date. The 2026 project budget was raised to $41 million from $31 million as investments originally planned for 2027 were brought forward.
  • Capital Investment and Exploration Continued2026 CapEx guidance was raised 10% to $420 million, primarily for higher mine development at Aripuanã, accelerated tailings-facility investment at Cerro Pasco, and the stronger Brazilian real. The company invested $111 million in CapEx during the quarter and $272 million year-to-date, about 65% of the new guidance. Exploration and project evaluation spending was $21 million, up 24% from the second quarter, with a faster pace of drilling; the full-year exploration budget remains $86 million.
  • Operating Cash Flow IncreasedOperating cash flow before working capital was $306 million, up 7% from the second quarter and 50% from last year. The company expects Cajamarquilla's metal inventory to unwind through fourth-quarter sales.
  • Liquidity and Debt Maturity Profile Remained SolidNexa ended the quarter with $735 million of available liquidity, including its undrawn $320 million revolving credit facility. Only 8% of debt, or $136 million, matures through the end of 2027, while average debt maturity is 6.8 years at an average cost of 6.7%.
  • Zinc and Copper Market Fundamentals Were SupportiveThe LME zinc price averaged $3,825 per ton, up 35% from a year ago and at its highest level since 2022. The LME copper price averaged $14,104 per ton, up 44% year-over-year and reaching a record in September. Management said tight concentrate supply and low refined inventories should continue supporting zinc prices, while copper demand should remain structurally strong.
  • Precious-Metal Prices Supported Byproduct CreditsSilver averaged $62.6 per ounce, up 59% from a year ago, and gold averaged $4,262 per ounce, up 23% year-over-year. Nexa expects to produce 10 million to 11 million ounces of silver this year, and management said silver and gold byproduct credits continue lowering unit cash costs at polymetallic operations.
  • Safety Performance Improved Year-over-Year in the QuarterThe recordable injury frequency rate improved to 1.34 from 1.50 a year ago. The company continued reinforcing critical-risk controls, including fatigue monitoring at Cerro Pasco and the Line of Fire campaign at El Porvenir and Atacocha.
  • ESG and Climate Preparedness Initiatives AdvancedNexa continued health campaigns, higher-education scholarships, and a new community contact channel in Peru. It advanced new uses for jarosite, Waelz Aggregate, and pyrite, expanded dry-stacking tailings capacity at Aripuanã, and reviewed El Niño preparedness plans. There was no El Niño impact in the quarter.
  • Boliden Transaction Continued Toward Expected ClosingManagement said the transaction involving Votorantim's sale of its controlling stake in Nexa to Boliden is progressing as expected, with closing expected in the first quarter of 2027 subject to customary approvals. Until closing, Nexa said it continues to operate as an independent company with its strategy, capital allocation priorities, and stakeholder commitments unchanged.

DE:NE0 Earnings History

DE:NE0 earnings history
Report DateFiscal QuarterForecast / EPSLast Year's EPSEPS YoY ChangePress Release
Feb 17, 20272026 (Q4)0.68-0.61――
Oct 29, 20262026 (Q3)0.56-0.430.33-230.56% (-0.76)
Aug 05, 20262026 (Q2)0.650.580.1481.82% (+0.48)
May 06, 20262026 (Q1)0.800.610.1482.61% (+0.51)
Feb 26, 20262025 (Q4)0.500.61-0.71185.26% (+1.32)
Oct 30, 20252025 (Q3)0.320.330.021700.00% (+0.31)
Jul 31, 20252025 (Q2)0.160.100.14-27.63% (-0.04)
Apr 29, 20252025 (Q1)0.020.10-0.16163.89% (+0.27)
Feb 20, 20252024 (Q4)0.26-0.71-0.01-7700.00% (-0.70)
Oct 31, 20242024 (Q3)0.120.02-0.39104.65% (+0.41)