Lucara Diamond (LKT) Q3 2026 Earnings Report

2 Followers

DE:LKT Q3 2026 EPS Results

Actual EPS
EUR 0.00
Consensus EPS
-EUR 0.01
Beat/Miss
Beat by +EUR 0.01
One Year Ago EPS
EUR 0.02

DE:LKT Q3 2026 Revenue Results

Actual Revenue
EUR 54.39M
Expected Revenue
―
Beat/Miss
―
YoY Revenue Growth
+21.27%

Earnings Announcement Details

Quarter
Q3 2026
Date
11/13/2026
Time
After Close
Conference Call
Friday, November 13, 2026
DE:LKT Upcoming Earnings

Lucara Diamond's next earnings date is estimated for February 23, 2027, based on past reporting schedules.

Q3 2026 Earnings Call Audio

No earnings call audio is available for this earnings event.

Q3 2026 Earnings Slide Deck

No slide deck is available for this earnings event.

Q3 2026 Earnings Call Summary

Q3 2026
Earnings Call Date:Nov 13, 2026|% Change Since:-1.43%|
Earnings Call Sentiment|Positive

The call was strongly positive, supported by higher Q3 revenue, increased full-year revenue guidance, improved operating cash generation, exceptional large-stone recoveries, lower operating-cost guidance, and substantial progress on the underground project. The main challenges were the depletion of the open pit, weather-related mining delays, higher fuel and power costs, lower average price per carat due to tender mix, and weaker-than-expected color performance from the blue stone.

Company Guidance

The company increased 2026 revenue guidance from $100 million to $130 million to $140 million to $160 million and reduced operating cost guidance to $24 per tonne to $26 per tonne, also restated at the end as $24 million to $26 million; the open pit is completely exhausted, with a small amount of open pit ore expected in Q4 of 2026 and the majority of material through year-end coming from historically mined stockpile material, while the better part of 7 million to 8 million tonnes of run-of-mine material could run for a full 2 years. Underground lateral development is being ramped up to 400, 600 and then 800 meters a month, with access to the kimberlite expected probably early in 2027, somewhere in Q1, underground production expected to supplement stockpile material probably as early as Q3 next year, and the shafts capable of 3 million tonnes per annum; rock winders are currently running at 8 meters per second, are expected to run at 14 meters a second, or 50 kilometers an hour, during normal production, and roughly about $40 million is expected in Q4 from the stones.

  • Strong Q3 Revenue and Updated GuidanceQ3 revenue was $61.1 million, compared with $51 million in the prior year, reflecting the sale of 113,000-plus carats including the 1,300-carat Type IIa diamond. Year-to-date revenue reached $124 million. Full-year 2026 revenue guidance was increased from $100 million to $130 million to $140 million to $160 million, an increase of more than $30 million at the upper end.
  • Improved Operating Cash GenerationQ3 net cash generated from operating activities, including working capital movements, was $35 million versus $15 million in the prior year, an increase of approximately 133%. Year-to-date operating cash generation was $32 million versus $28 million, an increase of approximately 14%.
  • Additional Cash Expected from Large-Diamond SalesProceeds from the 1,300-carat diamond and the other notable stones discussed had not yet been included in cash and were estimated to add roughly $40 million to the cash balance, with the proceeds expected in Q4.
  • Exceptional Special-Diamond RecoveriesLucara recovered 163 special stones of more than 10.8 carats during the quarter, including its 10th stone exceeding 1,000 carats and a further eight stones exceeding 100 carats. Total diamond recovery was just under 97,000 carats.
  • Notable Type IIa Diamond RecoveriesIn addition to the 1,300-carat Type IIa stone, the company highlighted a 146-carat white Type IIa stone, a 316-carat stone that was cleaved by the process plant, and a 115-carat stone.
  • Lower Operating-Cost GuidanceOperating-cost guidance was reduced to $24 per tonne to $26 per tonne. Management attributed the reduction primarily to increased throughput, as weathered stockpile material moves through the plant extremely quickly.
  • Underground Project Progressing on Budget and ScheduleUnderground project costs remained on budget and on schedule. Q3 expenditures were $40 million, leaving remaining costs of $245 million, largely consisting of contracted lateral-development costs, equipment, and infrastructure procurement.
  • Transition to Lateral Development CompletedShaft construction was completed and the project transitioned 100% to lateral development. Group R was onboard and ramping up, while the conveyors and rock winders were licensed during the quarter, allowing equipment to be moved underground and lateral development to proceed at pace.
  • Underground Development MilestonesMore than 2,000 meters of lateral development had been completed by quarter-end. Development is being ramped up to 400, 600, and then 800 meters per month, with access to the kimberlite expected probably in Q1 2027.
  • Early Completion of Critical Ore PassThe ore pass from the 470 level down to the 285 level was completed in September, quite a bit ahead of schedule. The raise bore was completed within 0.5 meter of its target.
  • Shaft Capacity and Licensing MilestonesThe shafts were handed over to operations, and the Department of Mines licensed both the conveyances and rock winders. The rock winders were operating at 8 meters per second and had been tested to 14 meters per second, with the shafts expected to enable underground production of 3 million tonnes per annum.
  • Strong Project Safety PerformanceThe underground project recorded a Total Recordable Injury Frequency Rate of 0.6, below the target of 0.9.
  • Ventilation and Underground Working ConditionsSurface ventilation was completed after quarter-end, with one fan operating sustainably at around 160 cubic meters per second. The bulk air cooler was operating at about 12 degrees Celsius, while average underground working conditions were about 21 degrees Celsius in Botswana weather exceeding 38 degrees Celsius.
  • Equipment Deployment ProgressA full fleet of equipment was operating across the four underground levels, and about 90% of ancillary equipment had been received, with only items such as Spraymecs and additional charge units still outstanding.
  • Favorable Underground Rock ConditionsAlthough the granite contact area had been expected to have fair to poor rock conditions, management reported that conditions were much better and that the rock quality, blasting conditions, and installed support were performing well.
  • Stockpile Provides Extended Processing RunwayThe company has the better part of 7 million to 8 million tonnes of run-of-mine stockpile material, described as material that had not previously been processed. Management said this could support a full two years of processing, while underground material is expected to begin supplementing the stockpile as early as Q3 next year.
  • Water-Management Infrastructure AdvancingWater structures encountered underground had been successfully grouted, including structures producing up to 60 cubic meters per hour. An LM90 drill was delivered underground for an advanced dewatering campaign. Six SP200 pumps were expected by year-end and a further six in the first quarter of next year, bringing total pumping capacity to around 300-plus cubic meters per hour.
  • Active Environmental Water ManagementTwo evaporators were operating 23 hours a day at approximately 50% to 60% efficiency, each handling about 110 cubic meters per hour, with four additional evaporators on order. Management stated that the water was very salty and therefore could not simply be discharged into the environment.
  • Positive Developments in Natural-Diamond DemandManagement reported some positive movement in the natural-diamond market and said Lucara's guidance increase, together with that of another large-stone producer, demonstrated resilience in the top end of the market.
  • Large-Stone Demand in the United StatesThe United States was described as a significant market for high-value stones, particularly diamonds of 20 carats and above. The Middle East also continued to be a market for larger stones, with Abu Dhabi identified as a focus for high-value jewelry.
  • Potential Value from the 1,300-Carat StoneThe initial polished value for the 1,300-carat stone had been agreed, and management said it was hoping to see an uplift in value once the polished stone was sold.

DE:LKT Earnings History

DE:LKT earnings history
Report DateFiscal QuarterForecast / EPSLast Year's EPSEPS YoY ChangePress Release
Feb 23, 20272026 (Q4)-0.01-0.01――
Nov 13, 20262026 (Q3)-0.010.000.02-100.00% (-0.02)
Aug 07, 20262026 (Q2)0.010.010.03-66.67% (-0.02)
May 07, 20262026 (Q1)0.00-0.010―
Mar 04, 20262025 (Q4)0.040.010.07-87.50% (-0.06)
Nov 13, 20252025 (Q3)0.000.020―
Aug 08, 20252025 (Q2)0.030.030.030.00% (+0.00)
May 10, 20252025 (Q1)0.000.00-0.02100.00% (+0.02)
Feb 22, 20252024 (Q4)0.010.07-0.06214.29% (+0.14)
Nov 14, 20242024 (Q3)0.050.000.02-100.00% (-0.02)

The table shows recent earnings report dates and whether the forecast was beat or missed. See the change in forecast and EPS from the previous year.

Beat Missed