Ameresco (4AM) Q2 2026 Earnings Report
DE:4AM Q2 2026 EPS Results
- Actual EPS
- EUR 0.18
- Consensus EPS
- EUR 0.18
- Beat/Miss
- Beat by +EUR 0.00
- One Year Ago EPS
- EUR 0.24
DE:4AM Q2 2026 Revenue Results
- Actual Revenue
- EUR 461.55M
- Expected Revenue
- EUR 416.52M
- Beat/Miss
- Beat by +EUR 45.03M
- YoY Revenue Growth
- +9.14%
Earnings Announcement Details
- Quarter
- Q2 2026
- Date
- 08/03/2026
- Time
- After Close
- Conference Call
- Monday, August 3, 2026
Ameresco's next earnings date is estimated for November 9, 2026, based on past reporting schedules.
Q2 2026 Earnings Call Audio
Q2 2026 Earnings Slide Deck
Q2 2026 Earnings Call Summary
The call conveyed a largely positive outlook driven by record awards, substantial backlog growth, improved margins, growing energy asset and O&M businesses, and strengthened capital via the Neogenyx JV. The company acknowledged near-term cash conversion and working capital timing pressures, modest GAAP profitability impacted by asset growth and transaction-related non-controlling interests, and execution risks tied to permitting, supply chain, and project timelines for large data center opportunities. Overall, the upside from robust awards, diversified recurring revenue streams, and financing support outweigh the near-term operational and timing challenges.
Management reaffirmed full‑year 2026 guidance across all metrics while raising non‑GAAP EPS guidance to $1.15–$1.35 (driven by an expected tax‑benefit rate of 25%–40% tied to a planned H2 accounting change for transferable tax credits); they expect awarded backlog to convert to revenue over the next 3–4 years and cited record Q2 new awards of $1.8B ($1.2B data centers, $600M other) with awarded backlog up 65% to $4.4B and total project backlog up 32% to $6.7B. Management said the second half should follow a normal seasonal cadence weighted toward Q4, is prioritizing cash conversion, and highlighted balance‑sheet flexibility with $138M unrestricted cash, $385M total corporate debt (3.2x leverage vs a 3.5x covenant) and $471M of new financing commitments (including $400M related to the Neogenyx JV).
- Record New AwardsNew awards reached a record $1.8 billion for the quarter, driven by $1.2 billion in data center awards and $600 million across other markets.
- Backlog ExpansionAwarded project backlog increased 65% to $4.4 billion and total project backlog rose 32% to $6.7 billion, providing multi-year conversion visibility.
- Revenue Growth and Strong Quarter ResultsTotal revenue was $515 million, up 9% year-over-year; project revenue was $381 million, up 6% YoY. Adjusted EBITDA grew 12% to $62.8 million.
- Energy Asset and O&M MomentumEnergy asset revenue increased 21% to $76 million; Ameresco placed an additional 32 MW into operation, reaching 822 MW operating (513 MW in development/construction). O&M revenue rose 29%, with long-term O&M backlog exceeding $1.5 billion and service provided for over 2.5 GW of third-party solar and battery storage.
- Improved MarginsGross margin improved to 17.7%, a meaningful sequential and year-over-year improvement attributed to favorable mix and execution.
- Capital Strengthening and Neogenyx JVClosed Neogenyx JV with HASI, securing significant external capital. Secured $471 million of new financing commitments in the quarter (including $400 million related to Neogenyx). Unrestricted cash increased to $138 million and corporate leverage was 3.2x, below the 3.5x covenant.
- Strategic Wins and Major Project CompletionsBrought online the 250 MW Napanee battery energy storage system in Canada and energized a 560 MW solar project in Greece. Announced first successful delivery of RNG into European compliance markets and a rebranding/repositioning into two core pillars (Power Infrastructure; Building & Public Infrastructure).
- Data Center Pipeline and Competitive PositioningAdded three new data center projects to awarded backlog (bringing total awarded data center projects to five plus Lemoore), representing over 1 GW of power generation. Management highlighted strong demand from hyperscalers, neoclouds, developers and expects awards-to-contracts conversion typically in 6–24 months and full implementation over subsequent 1–3 years.
- Raised Non-GAAP EPS GuidanceReaffirmed full-year 2026 guidance and increased non-GAAP EPS guidance to $1.15–$1.35, reflecting an expected tax benefit rate of 25%–40% and an accounting policy change for transferable tax credits.
DE:4AM Earnings History
| Report Date | Fiscal Quarter | Forecast / EPS | Last Year's EPS | EPS YoY Change | Press Release |
|---|---|---|---|---|---|
| Nov 09, 2026 | 2026 (Q3) | 0.51- | 0.31 | ― | ― |
| Aug 03, 2026 | 2026 (Q2) | 0.180.18 | 0.24 | -25.93% (-0.06) | |
| May 04, 2026 | 2026 (Q1) | -0.26-0.30 | -0.1 | -200.00% (-0.20) | |
| Mar 02, 2026 | 2025 (Q4) | 0.290.35 | 0.79 | -55.68% (-0.44) | |
| Sep 30, 2025 | 2025 (Q3) | 0.230.31 | 0.29 | 9.38% (+0.03) | |
| Aug 04, 2025 | 2025 (Q2) | 0.070.24 | 0.09 | 170.00% (+0.15) | |
| May 05, 2025 | 2025 (Q1) | -0.23-0.10 | -0.09 | -10.00% (-0.01) | |
| Feb 27, 2025 | 2024 (Q4) | 0.710.79 | 0.62 | 27.54% (+0.17) | |
| Nov 07, 2024 | 2024 (Q3) | 0.460.29 | 0.36 | -20.00% (-0.07) | |
| Aug 05, 2024 | 2024 (Q2) | 0.170.09 | 0.13 | -33.33% (-0.04) |
The table shows recent earnings report dates and whether the forecast was beat or missed. See the change in forecast and EPS from the previous year.