Bannerman Energy (BMN) Q4 2026 Earnings Report

97 Followers

AU:BMN Q4 2026 EPS Results

Actual EPS
-AUD 0.03
Consensus EPS
-AUD 0.01
Beat/Miss
Missed by -AUD 0.02
One Year Ago EPS
-AUD 0.01

AU:BMN Q4 2026 Revenue Results

Actual Revenue
AUD 0
Expected Revenue
AUD 0
Beat/Miss
Met expectations
YoY Revenue Growth
―

Earnings Announcement Details

Quarter
Q4 2026
Date
09/23/2026
Time
After Close
Conference Call
Wednesday, September 23, 2026
AU:BMN Upcoming Earnings

Bannerman Energy's next earnings date is estimated for March 10, 2027, based on past reporting schedules.

Q4 2026 Earnings Call Audio

No earnings call audio is available for this earnings event.

Q4 2026 Earnings Slide Deck

No slide deck is available for this earnings event.

Q4 2026 Earnings Call Summary

Q4 2026
Earnings Call Date:Sep 23, 2026|% Change Since:-22.83%|
Earnings Call Sentiment|Positive

The call was strongly positive, driven by significant financing progress, robust liquidity, construction advancing on budget and schedule, strong safety performance, supportive long-term uranium pricing and confidence in the project timeline and capital cost. The main challenges were the two remaining Chinese regulatory approvals, the need to implement systems for challenging procurement targets and a quiet spot market.

Company Guidance

Management said final CPs and transaction completion should be expected during quarter 3 of 2026, with the NDRC and Ministry of Commerce approval in China itself the only outstanding CP; next quarter’s expenditure will be “very similar” to this quarter’s, followed post-deal completion by “significantly accelerated expenditure,” and Bannerman is “100% aligned” with its September 28 commissioning date. The $27 million reimbursement is linked to a $16 million capital-expenditure cap, while the $353 million estimate plus or minus 10% is considered secure; Bannerman and CNOL agreed to achieve a 90% Namibian employee ratio within 5 years, Etango-16 is expected 5 years after production commences at Etango-8, and the company would begin actively and aggressively seeking offtake contracts probably 6 months before production, with market terms sounding like floors in mid-70s and ceilings between [ 130 and 155 ], and fixed price escalated contracts just north of a [ 100 ].

  • Strategic Financing ProgressSignificant progress was made on the strategic financing conditions precedent, with confidence that the final conditions precedent and transaction completion should occur during quarter 3 of 2026.
  • Strong Liquidity and Cash ControlThe company ended the quarter with $53 million of cash assets and an additional $11.5 million of liquid assets. It has committed an additional $36 million to ongoing site contracts, while total project spend to date stands at $69 million.
  • Supportive Long-Term Uranium PriceThe long-term uranium price increased during the quarter and is now sitting at $97 per pound, which management described as supportive of the business.
  • Construction Progress and Safety PerformanceConstruction activity continued to track against budget and schedule, with over 560 personnel working on site. The project achieved 1.1 million LTI-free man hours, reflecting the team's focus on safety and safe construction practices.
  • Bulk Earthworks Near CompletionBulk earthworks progressed to 92% complete and the contract is expected to be finished during the next quarter.
  • Advancement of Crusher and Dry Plant ConstructionThe primary crusher concrete structure has progressed above ground level and is approaching completion. Concrete work is also progressing significantly on the dry plant, including the silo and the secondary and tertiary screening building.
  • Permanent Water Supply ProgressPhase 1 of the permanent water supply line contract reached 87% completion. The company has secured its portion of the supply-line capacity and the last existing fitting in the Swakopmund reservoir.
  • Conditions Precedent Completed in NamibiaCNOL shareholder approval and Namibian Competition Commission approval were completed. Infrastructure-related conditions precedent were also met through the NamWater agreement, the asset storage facility lease and the previously signed power contract.
  • Namibian Employment and Procurement CommitmentsCNOL and Bannerman agreed to achieve a 90% Namibian employee ratio within 5 years. Management said the company is currently achieving its targets in terms of ratios and is confident it can meet the commitments, including procurement targets, with systems put in place over the 5-year period.
  • CapEx Spending Expected to Remain Similar in the Near TermExpenditure in the next quarter is expected to be very similar to the current quarter. Lower earthworks spending is expected to be supplemented by the five long-lead mechanical equipment items placed for the dry plant.
  • Post-Completion Construction AccelerationFollowing deal completion, expenditure is expected to accelerate significantly with the placement of structural steel contracts, which have been adjudicated and are ready for placement. Management remains 100% aligned with its September 28 commissioning date, and earlier deal completion could have a positive impact on the schedule.
  • Reimbursement Plan Remains on TrackExpenditure is tracking the original plan for the $27 million CNOL reimbursement. The reimbursement is linked to a $16 million capital expenditure cap through the end of September; management may accelerate spending to reach the cap but stated it will not overspend the $16 million.
  • Etango Capital Cost Tracking WellThe project is tracking well against the $353 million estimate and its plus or minus 10% range. The five mechanical equipment orders for the dry plant came in on budget and a little under the original budget, while pre-agreed escalation formulas protected pricing despite the war in the Middle East. Management said the $353 million plus or minus 10% is secure.
  • Schedule Float Built Into Dry Plant ContractsThe five dry plant contracts were placed to create additional float in the construction schedule. Management said they are not on the critical path but are being delivered well within it to provide protection against back-end unknowns.
  • Expansion Strategy Favors Etango-16Management said the strategy is heading toward the expansion case rather than the extension case. The plan is for Etango-16 to enter production 5 years after Etango-8 commences production, with both plants operating simultaneously after Etango-8 production ends.
  • Secured and Diversified Water SupplyThe NamWater contract covers supply from both the existing desalination plant and the announced new desalination plant. The new plant is due to be commissioned before the mine is completed, while management stated that the existing desalination plant has sufficient water for the project.
  • Offtake Position Provides Contracting FlexibilityThe company has secured 6% offtake with CNOL, giving it time to begin actively seeking additional contracts approximately 6 months before production. Management said this timing may allow significantly higher pricing than is available now; market indications included floors in the mid-70s, ceilings between [ 130 and 155 ], and fixed-price escalated contracts just north of a [ 100 ].
  • Positive Assessment of Namibian ContractorsFollowing site visits, management said the Namibian contractors are world class and are doing a fantastic job constructing the project in line with the planned strategy.

AU:BMN Earnings History

AU:BMN earnings history
Report DateFiscal QuarterForecast / EPSLast Year's EPSEPS YoY ChangePress Release
Mar 10, 20272027 (Q2)-0.02-0――
Sep 23, 20262026 (Q4)-0.01-0.03-0.01-262.50% (-0.02)
Mar 03, 20262026 (Q2)-0.01-0.00-0.0276.47% (+0.01)
Sep 24, 20252025 (Q4)-0.01-0.01-0.0265.22% (+0.01)
Mar 05, 20252025 (Q2)―-0.02-0.0458.54% (+0.02)
Sep 19, 20242024 (Q4)―-0.02-0.01-91.67% (-0.01)
Mar 06, 20242024 (Q2)―-0.04-0.02-105.00% (-0.02)
Sep 24, 20232023 (Q4)―-0.01-0.0120.00% (+0.00)
Mar 08, 20232023 (Q2)―-0.02-0.01-66.67% (-0.01)
Sep 23, 20222022 (Q4)―-0.01-0.01-50.00% (-0.01)

The table shows recent earnings report dates and whether the forecast was beat or missed. See the change in forecast and EPS from the previous year.

Beat Missed