Allied Gold Corporation earnings date
Allied Gold Corporation (AAUC) Q3 2026 Earnings Report
AAUC Q3 2026 EPS Results
- Actual EPS
- $0.37
- Consensus EPS
- $0.21
- Beat/Miss
- Beat by +$0.16
- One Year Ago EPS
- $0.29
AAUC Q3 2026 Revenue Results
- Actual Revenue
- $351.68M
- Expected Revenue
- $350.00M
- Beat/Miss
- Beat by +$1.68M
- YoY Revenue Growth
- +19.10%
Earnings Announcement Details
- Quarter
- Q3 2026
- Date
- 11/04/2026
- Time
- After Close
- Conference Call
- Wednesday, November 4, 2026
Allied Gold Corporation's next earnings date is estimated for March 31, 2027, based on past reporting schedules.
Q3 2026 Earnings Call Audio
No earnings call audio is available for this earnings event.
Q3 2026 Earnings Slide Deck
Q3 2026 Earnings Call Summary
The call was strongly positive, driven by Kurmuk entering production, expected near-term ramp-up, strong liquidity, solid quarterly financial results, significant production growth plans and anticipated shareholder returns. The main challenges were Sadiola's high all-in sustaining costs, diesel-related cost pressure and operational improvements needed after deferred work during the Zijin transaction, but management expressed confidence in improving production and declining unit costs.
Kurmuk production is expected to be 25,000-35,000 oz in November and December, increasing to 55,000-65,000 oz in the first quarter of next year, 240,000-270,000 ounces for all of 2027, and approximately 300,000 ounces in 2028; the company expects commercial production roughly by the end of the year and nameplate capacity early next year, with an average of 300,000 ounces of production per year for the initial four years and plans to extend that for longer. Company-wide production is expected to step up next year to 615,000-670,000 ounces of gold, toward a sustainable platform of approximately 800,000 ounces annually by 2029, supported by Kurmuk ramping up toward 300,000 ounces annually by 2028, Sadiola’s phased expansion toward 300,000-400,000 ounces, and at least 200,000 ounces from Côte d’Ivoire; Sadiola’s modular expansion is initially to at least 7 million tons per year, reaching 250,000-275,000 ounces of gold per year and as much as 300,000 ounces of gold per year in certain years, while Bonikro’s mine life exceeds 10 years with production of up to 120,000 ounces per year. Sadiola production is expected to increase about 20%-25% from Q3 to Q4, and unit costs are expected to decline through this quarter and into the coming quarters into 2027. The company expects a base dividend early next year, anticipates the start in 2027 of a share buyback program, and intends to purchase for cancellation up to 10% of the public float, subject to the approval of the Toronto Stock Exchange; an updated Sadiola feasibility study and capital estimate is expected in early 2027, and the pre-leach thickener is expected to be commissioned in the second quarter.
- Strong Quarterly Operating PerformanceManagement reported strong and expected operating results for the quarter. Bonikro exceeded plan, Agbaou delivered strong results and was well on plan, and Sadiola production compared favorably with plan and the prior-year quarter.
- Kurmuk Entered ProductionKurmuk commissioning activities began during the quarter, ore was introduced into the processing plant, and the mine is now in production. Output is expected to ramp up through the remainder of the year and beyond.
- Solid Cash Generation and LiquidityThe company ended the quarter with approximately $379 million in cash and generated $116 million of operating cash flow. Total liquidity, including the undrawn revolving credit facility, was $429 million.
- Revenue, EBITDA and Earnings GrowthRevenue increased to $358 million, supported by an average realized gold price of just under $3,900 per ounce and strong gold production. Adjusted EBITDA was approximately $140 million, while adjusted net earnings were $49 million, or $0.37 per share.
- Bonikro Delivered Strong Production and CostsBonikro produced approximately 28,600 ounces at all-in sustaining costs of $1,670 per ounce, benefiting from higher grades and improved recoveries.
- Agbaou Met Plan with Better-Than-Expected CostsAgbaou produced 20,300 ounces at all-in sustaining costs of $2,384 per ounce. Production was in line with plan and costs were better than expected.
- Sadiola Improvement Program UnderwaySadiola produced approximately 42,300 ounces at all-in sustaining costs of $2,876 per ounce. The company has begun implementing improvement initiatives deferred during the Zijin transaction process, including equipment availability, grade-control work, contract changes related to fleet reliability and availability, and the introduction of higher-grade fresh and oxide ore. Production is expected to increase and unit costs are expected to decline through the current quarter and into the coming quarters into 2027.
- Expected Sadiola Fourth-Quarter ImprovementManagement said higher-grade ore is entering the mine sequence and expects a significant increase in Sadiola production in the fourth quarter. Production is expected to increase by about 20%-25% from Q3 to Q4, mostly as a result of improvements to grade.
- Kurmuk Production Outlook and Low-Cost PositionKurmuk production is expected to be 25,000-35,000 ounces in November and December, increasing to 55,000-65,000 ounces in the first quarter of next year. The outlook for 2027 is 240,000-270,000 ounces, increasing to approximately 300,000 ounces in 2028. Management expects Kurmuk to be the company's lowest-cost operation and to contribute disproportionately more cash flow as production ramps up.
- Kurmuk Stockpile Ahead of ScheduleKurmuk's stockpile was approximately 1.5 million tons, representing roughly three months of stockpile and ahead of schedule for commercial production. Grades were comparable to or better than reserve grade, with half of the stockpile at significantly higher grade than reserve grade; medium- and high-grade ore averaged around 1.7 to 1.8 grams per ton.
- Kurmuk Processing Flexibility and Exploration UpsideThe Kurmuk processing plant has capacity of up to 6.4 million tons per year, providing operational flexibility to optimize production as the mine ramps up. Continued exploration has identified extensions of existing ore bodies, including Ashashire, new mineralized areas, and recent drilling grades better than reserve grade. Management expects to upgrade Proven and Probable Reserves and seek to extend average production of roughly 300,000 ounces beyond the initial four years.
- Kurmuk Power Infrastructure ProgressKurmuk is connected to the grid and currently has diesel-generator backup. Full power to run the plant at nameplate is expected by the third week to fourth week of November following installation of the STATCOM line-stabilization equipment. Management expects this to support commercial production by the end of the year and nameplate production soon after.
- Significant Production Growth OutlookThe company plans to more than double production from approximately 379,000 ounces last year, roughly the production expected this year, toward a sustainable platform of approximately 800,000 ounces annually by 2029. Next year's expected production is 615,000-670,000 ounces, described as a full 54% increase to this and to last year. Growth is supported by Kurmuk ramping toward 300,000 ounces annually by 2028, the phased expansion of Sadiola toward 300,000-400,000 ounces, and sustained production of at least 200,000 ounces from Côte d'Ivoire.
- Côte d'Ivoire and Bonikro Mine-Life StrengthThe Bonikro and Agbaou Côte d'Ivoire complex continued to perform well and is expected to support at least 200,000 ounces of production. Bonikro's mine life now exceeds 10 years, with production of up to 120,000 ounces per year.
- Sadiola Expansion and Power InitiativesSadiola's modular expansion is being advanced initially to at least 7 million tons per year, supporting 250,000-275,000 ounces of gold per year and as much as 300,000 ounces in certain years depending on grade. A pre-leach thickener is in progress, recovery increases are underway to support production of at least 200,000 ounces per year, and a power solution involving solar, upgraded generators and a heavy fuel engine is expected to improve available power, reliability and costs.
- Expected Cash-Flow Growth and Shareholder ReturnsManagement expects improving costs and greater contribution from Kurmuk and the other mines to drive cash-flow growth that exceeds the rate of production growth. The company is progressing a shareholder-return policy that includes a base dividend expected early next year and an anticipated share buyback program starting in 2027, subject to board and Toronto Stock Exchange approval. The proposed normal course issuer bid could purchase for cancellation up to 10% of the public float.
- Upcoming Development and Resource UpdatesThe company expects to provide an updated feasibility study and capital estimate for the Sadiola modular expansion in early 2027, along with an annual mineral reserve and mineral resource update. It also expects to commission the Sadiola pre-leach thickener in the second quarter.
- Supply-Chain ResilienceManagement reported no disruption or risk of disruption to supply lines and logistics from geopolitical events. The company has its own license for fuel importation in Ethiopia, uses multiple delivery routes, and sources Sadiola's supply chain from Senegal.
- Gold Collar Expirations Increase Price ExposureThe remaining gold collars entered into for the development of Kurmuk are expected to expire in December. Management stated that this will increase the company's exposure to the prevailing gold price and remove the revenue impact of those collars.
AAUC Earnings History
| Report Date | Fiscal Quarter | Forecast / EPS | Last Year's EPS | EPS YoY Change | Press Release |
|---|---|---|---|---|---|
| Mar 31, 2027 | 2026 (Q4) | 0.71- | 0.56 | ― | ― |
| Nov 04, 2026 | 2026 (Q3) | 0.210.37 | 0.29 | 27.59% (+0.08) | |
| Aug 05, 2026 | 2026 (Q2) | 0.340.44 | 0.14 | 214.29% (+0.30) | |
| May 14, 2026 | 2026 (Q1) | ―-0.47 | 0.42 | -211.90% (-0.89) | |
| Mar 31, 2026 | 2025 (Q4) | 0.320.39 | 0.42 | -7.14% (-0.03) | |
| Nov 05, 2025 | 2025 (Q3) | 0.380.29 | 0.6 | -51.67% (-0.31) | |
| Aug 06, 2025 | 2025 (Q2) | 0.290.14 | 0.19 | -27.46% (-0.05) | |
| May 07, 2025 | 2025 (Q1) | 0.470.42 | 0 | ― | |
| Mar 26, 2025 | 2024 (Q4) | -0.210.09 | -0.06 | 250.00% (+0.15) | |
| Nov 07, 2024 | 2024 (Q3) | 0.200.60 | 0.03 | 1900.00% (+0.57) |
The table shows recent earnings report dates and whether the forecast was beat or missed. See the change in forecast and EPS from the previous year.