Iluka Resources Limited earnings date
Iluka Resources Limited (ILZ) Q2 2026 Earnings Report
DE:ILZ Q2 2026 EPS Results
- Actual EPS
- -EUR 0.04
- Consensus EPS
- -EUR 0.06
- Beat/Miss
- Beat by +EUR 0.03
- One Year Ago EPS
- EUR 0.13
DE:ILZ Q2 2026 Revenue Results
- Actual Revenue
- EUR 288.60M
- Expected Revenue
- EUR 181.05M
- Beat/Miss
- Beat by +EUR 107.55M
- YoY Revenue Growth
- -21.10%
Earnings Announcement Details
- Quarter
- Q2 2026
- Date
- 08/18/2026
- Time
- After Close
- Conference Call
- Tuesday, August 18, 2026
Iluka Resources Limited's next earnings date is estimated for February 23, 2027, based on past reporting schedules.
Q2 2026 Earnings Call Audio
Q2 2026 Earnings Slide Deck
Q2 2026 Earnings Call Summary
The call presented several strong operational and financial positives: robust cash generation, a 42% reduction in mineral sands net debt, successful milestones at Balranald and substantial progress at the Eneabba refinery (60% complete and on-budget), plus initial rare earths commercial agreements. Offsetting these were notable execution challenges at Balranald that delayed consistent extraction rates, a statutory loss driven by inventory movements and idle charges, idled synthetic rutile capacity with uncertain restart timing, and mixed end-market demand (particularly in China). On balance, the positive cash, balance-sheet and commercial progress materially outweigh the operational and timing headwinds, but execution risks and demand softness warrant continued monitoring.
Guidance from the call highlighted that contracted sand prices rose to around $1,760 per tonne for Q3 and are expected to broadly hold at that level for the remainder of the year; mineral sands cash costs for 2026 are now guided to about $380 million and full‑year mineral sands CapEx to $115 million (H1 CapEx was $94 million, including $35 million reclassified from operating costs). The mineral sands business generated $247 million of operating cash flow and $200 million of free cash flow in H1, reducing mineral sands net debt by 42% to $273 million at 30 June; statutory results included $156 million of inventory movements and $41 million of idle charges. Inventories were drawn down (finished goods down ~74,000 tonnes of zircon sand and ~37,000 tonnes of synthetic rutile), Balranald has 2 rigs operational with first HMC shipment to Narngulu scheduled for September and ramping to target extraction rates expected in calendar 2027, and Eneabba refinery is 60% complete with total capex reaffirmed at $1.7–$1.8 billion, mineral commissioning slated for 2027, full access to a $1.65 billion EFA loan, and an Iluka equity contribution package of $214 million (including ~$82 million working capital expected in early 2027).
- Strong cash generation and balance sheet improvementMineral sands business generated $247 million of operating cash flow and $200 million of free cash flow in H1 2026. Mineral sands net debt reduced by 42% to $273 million at 30 June.
- Zircon pricing and market strengthContracted sand prices increased to around $1,760 per tonne for Q3 driven by supply tightness (Senegal fire, lower Indonesian exports and peer disruptions). Management expects prices to broadly hold at Q3 levels absent material demand or supply changes.
- Balranald commissioning delivered and ramp-up underwayBalranald commissioning was achieved with 2 mining rigs now operational, magnetic and non-magnetic heavy mineral concentrates produced to specification, and first heavy mineral concentrate shipment to Narngulu scheduled for September.
- Eneabba refinery execution and on-budget confidenceEneabba construction is 60% complete, majority of major equipment delivered, piping/electrical/I&E installation underway, progressive commissioning begun and management reaffirmed total capital budget of $1.7–$1.8 billion. Mineral commissioning (first feedstock) expected in 2027.
- Commercial progress in rare earthsExecuted first refined rare earths offtake agreement with a global automotive company and signed a concentrate supply agreement with VHM Resources (July), strengthening long-term feedstock position and de-risking refinery feed options.
- Inventory drawdown and finished goods positionFinished goods reduced with zircon down by 74,000 tonnes and synthetic rutile down by 37,000 tonnes in the half. Management noted total finished goods around 260,000 tonnes and outlined planned SR sales (c.73,000 tonnes) over next six months.
- Capital discipline and dividendFull year mineral sands CapEx updated to $115 million (H1 CapEx was $94 million). Company declared a $0.03 fully franked dividend consistent with capital allocation framework and distributed receipts from 20% Deterra Royalties stake.
DE:ILZ Earnings History
| Report Date | Fiscal Quarter | Forecast / EPS | Last Year's EPS | EPS YoY Change | Press Release |
|---|---|---|---|---|---|
| Feb 23, 2027 | 2026 (Q4) | -0.07- | -0.02 | ― | ― |
| Aug 18, 2026 | 2026 (Q2) | -0.06-0.04 | 0.13 | -126.42% (-0.17) | |
| Feb 17, 2026 | 2025 (Q4) | -0.11-0.02 | 0.15 | -113.04% (-0.16) | |
| Aug 19, 2025 | 2025 (Q2) | 0.100.13 | 0.2 | -31.61% (-0.06) | |
| Feb 18, 2025 | 2024 (Q4) | 0.120.15 | 0.21 | -30.30% (-0.06) | |
| Aug 20, 2024 | 2024 (Q2) | 0.160.20 | 0.3 | -35.15% (-0.11) | |
| Feb 20, 2024 | 2023 (Q4) | 0.150.21 | 0.34 | -38.89% (-0.13) | |
| Aug 22, 2023 | 2023 (Q2) | 0.310.30 | 0.43 | -28.87% (-0.12) | |
| Feb 20, 2023 | 2022 (Q4) | 0.390.34 | 0.27 | 28.57% (+0.08) | |
| Aug 23, 2022 | 2022 (Q2) | 0.640.43 | 0.18 | 130.93% (+0.24) |
The table shows recent earnings report dates and whether the forecast was beat or missed. See the change in forecast and EPS from the previous year.