Mawson Infrastructure Group announces that it has installed 2 additional substation transformers at its 100 MW Midland, PA site. These transformers will power the second 50MW of capacity at the facility, capable of holding up to 29,400 miners and producing up to 3.5 exahashes per second when fully deployed . The site is expected to be fully operational in early Q2, 2023 with these transformers being the final piece of infrastructure required, connecting the previously built out poles and wires and is expected to double the Mawson Self-mining and hosting operations, once our modular data centers and ASIC miners are fully deployed.